The countdown has started, there are still 3 weeks to go! All the companies working on the interior work are currently on the construction site at the same time. The furniture for the Stüva restaurant has been delivered and our lobby bar currently looks like a furniture warehouse. The railing has been installed on the new spiral staircase and the tiles have been laid and the walls plastered in the restaurant area. And the kitchen is also slowly taking shape. It remains exciting for the final spurt!