The days are getting colder and the construction site is still very busy. In the restaurant area on the ground floor, the floor has been replaced everywhere and some of the flooring has already been laid. The terrace at the former takeaway has been removed, and in the last few days it has been dug up and refilled. The large pit at the hotel entrance has been filled in so that concreting can begin soon. The apartments are also making good progress, and we have now reached the top floor here.